Kotobukiya to invest ¥1.66 billion in molds for new products

Kotobukiya Co., Ltd.Published
Investment¥1.7B
PhaseUnder construction
StartSep 2025
CompletionJun 2027
Construction
Today
20262027

About 9 months to scheduled completion.

Kotobukiya plans to invest ¥1.66 billion in molds at its outsourced manufacturing sites to support production of new products. The investment is scheduled to begin in September 2025 and be completed in June 2027, funded through internal funds and borrowings.

Project facts

Owner
Kotobukiya Co., Ltd.
Listing
7809 Tokyo
Facility
Factory/Plant
Sector
Other manufacturing
Investment
¥1.7B — total
Scale / capacity
Production of new products
Construction start
Sep 2025
Completion
Jun 2027
Announced
Sep 24, 2026

Figures and schedules are as announced by the company or the public body concerned; plans can change. Amounts that were not disclosed are recorded as not disclosed, never estimated.

Latest in Other manufacturingAll Other manufacturing →

Sanyo Shokai to relocate and build new Aomori coat factory in Towada

Other manufacturingAomoriPlanned

Sanyo Shokai will relocate and newly build its Sanyo Sewing Aomori Factory in Towada, Aomori, as part of its growth investment program. The new facility will manufacture coats and support product development and technology verification, with construction planned from 2027 and operations scheduled to begin in the first half of FY2028.

Nippon Shikizai opens Komoro cosmetics factory

Other manufacturingNaganoCompleted

Nippon Shikizai, a Japanese cosmetics ODM/OEM manufacturer, held the opening ceremony for its newly acquired Komoro factory in Nagano Prefecture. The facility handles filling, packaging and finishing for makeup products such as mascara and eye shadow, and began operations on September 3, 2026.

Kyocera completes Nagasaki Isahaya plant

Other manufacturingNagasakiCompleted¥68B

Kyocera opened its Nagasaki Isahaya Plant on September 1, 2026, with an opening ceremony planned for spring 2027. The first building is a six-story steel-frame structure with 80,799 sqm of floor area on a 150,000 sqm site, producing fine ceramic components and semiconductor packages; Kyocera plans approximately JPY 68 billion in investment through fiscal 2028 and targets JPY 25 billion in annual sales from the plant from fiscal 2030.

Ishihara Sangyo completes Blue Gene blue orchid development and production facility

Other manufacturingMieCompleted

Ishihara Sangyo completed and held the ceremony for a new Blue Gene blue orchid development and production facility at its Yokkaichi Plant on August 26, 2026. The facility comprises a sterile culture room for propagating seedlings, a high-temperature greenhouse for cultivation and a low-temperature greenhouse for inducing flowering, enabling integrated in-house development and stable supply of high-quality flask seedlings.