PostedProjectSectorLocationInvestmentPhase
2026.08.07Fujikura to build new SWR factory at its Sakura siteFujikura plans to build a new SWR factory at its Sakura Business Office in Sakura, Chiba, to expand capacity in its Information and Communications segment. Construction began in August 2025, with completion planned for FY2029; capacity is expected to increase approximately twofold.TelecomSakura, Chiba¥45BBuilding
2026.08.07Fujikura to build new SWR factory at Sakura siteFujikura plans a new SWR factory at its Sakura Operations site in Sakura, Chiba, for its Information and Communications business. The project began in August 2023, is scheduled for completion in June 2026, and is expected to increase capacity by 1.3 times.TelecomSakura, Chiba¥10.1BBuilding