JScopeJapan Capex

Kurimoto to upgrade ductile iron pipe production equipment at Sakai Plant

Steel & Non-ferrous MetalsOsaka

Kurimoto is investing in ductile iron pipe manufacturing equipment at its Sakai Plant in Sakai's Nishi Ward. The project began in April 2024 and is scheduled for completion in March 2027, funded with the company's own resources.

Company
Kurimoto, Ltd.
Investment
¥1.2B total planned investment
Location
Osaka, Sakai
Announced
Jun 24, 2026
Ticker
5602
Phase
construction
Construction start
Apr 1, 2024
Completion
Mar 1, 2027
Want the full picture?See what you get

Hanwa opens Tijuana coil center in Rosarito, Baja California

Steel & Non-ferrous MetalsMexicoCompleted

Hanwa established HANWA STEEL SERVICE TIJUANA, S.A. DE C.V. in Rosarito, Baja California, its second coil centre in Mexico, and began full operations in August 2026. The site covers 38,086 sqm with 9,420 sqm of buildings and cuts and sells thin steel sheet for the Tijuana-Mexicali border region, where manufacturers supplying the United States are concentrated. Coil-centre functions previously run from San Diego Vista Steel Service in the United States transfer to the new operation at the end of August 2026. No investment amount was disclosed.

Aichi Steel plans forging equipment investment at Tokai forging plant

Steel & Non-ferrous MetalsAichiUnder construction¥6.9B

Aichi Steel plans new forged-product manufacturing equipment and related facilities at its forging plant in Tokai, Aichi, under its Forge Company segment, with total planned investment of JPY 6.859 billion. Construction is scheduled to run from December 2023 to March 2030.

Aichi Steel plans new rolling equipment at Kariya plant

Steel & Non-ferrous MetalsAichiUnder construction¥1.3B

Aichi Steel plans to install rolling equipment and other facilities at its Kariya plant in Aichi, supporting its Stainless Steel Company segment, with total planned investment of JPY 1.278 billion. Construction is scheduled to run from July 2024 to October 2028.