Nissin completes Kobe Chemical Center logistics hub
Nissin has completed the Kobe Chemical Center in Kobe, Hyogo, and held its completion ceremony on October 8, 2026. The logistics facility addresses growing demand for hazardous-material storage in the Kansai region and includes refrigerated and ambient hazardous-material warehouses, a high-pressure gas warehouse, a general warehouse, outdoor storage, mobile racks, and emergency power generation.
Project facts
- Owner
- Nissin Corporation
- Listing
- 9066 Tokyo
- Facility
- Logistics facility
- Location
- Kobe, Hyogo, Japan
- Investment
- Not disclosed
- Scale / capacity
- 31,271.02 sqm site; 8,189.20 sqm total floor area
- Completion
- Oct 8, 2026
- Announced
- Oct 9, 2026
- Themes
- cold-chain
Figures and schedules are as announced by the company or the public body concerned; plans can change. Amounts that were not disclosed are recorded as not disclosed, never estimated.