Tatsuta Electric Wire will make additional capital investments at its Kyoto Plant in Fukuchiyama, Kyoto, to increase production capacity for leak-detection systems used in AI data centers and other facilities. The expansion will proceed in stages, with capacity expected to reach approximately 2.5 times the end-2026 level by September 2027, as demand for water-cooling infrastructure in AI data centers grows.

Project facts

Owner
Tatsuta Electric Wire Co., Ltd.
Listing
5809 Tokyo
Facility
Factory/Plant
Sector
Semiconductors & electronics
Location
Fukuchiyama, Kyoto, Japan
Investment
Not disclosed
Scale / capacity
Approximately 2.5 times the end-2026 production capacity
Completion
Sep 2027
Announced
Oct 9, 2026
Themes
AI-infrastructure

Figures and schedules are as announced by the company or the public body concerned; plans can change. Amounts that were not disclosed are recorded as not disclosed, never estimated.

More from Tatsuta Electric Wire Co., Ltd.2 projectsCompany profile →

Also in Kyoto10 projectsOn the map →

Latest in Semiconductors & electronicsAll Semiconductors & electronics →

Murata Manufacturing completes new production building at Ho Chi Minh factory in Vietnam

NewSemiconductors & electronicsVietnamCompleted¥3B

Murata Manufacturing Vietnam invested approximately ¥3 billion to build a new production building at its Ho Chi Minh factory site, with construction running from May 2025. The building was completed and formally opened on October 8, 2026, and will support production of coil products for consumer electronics and automotive applications, with operations starting progressively.

Toshiba Information Equipment Philippines expands HDD production lines for nearline drives

Semiconductors & electronicsPhilippinesCompleted

Toshiba Information Equipment Philippines has expanded production lines at its Laguna Technopark facility and shipped its first nearline HDDs for data centers. The company aims to approximately double total annual production capacity on a storage-capacity basis by FY2027 versus FY2025, supporting demand from generative AI and cloud services.

Okayama Murata Manufacturing to make major equipment investment at its Okayama site

Semiconductors & electronicsOkayamaPlanned¥9B

Okayama Prefecture announced that Okayama Murata Manufacturing will use the prefecture's Large Investment and Base Development Promotion Subsidy for an equipment investment of approximately 9 billion yen to expand the ceramic raw material production line at its main plant in Setouchi, Okayama. Construction is scheduled to start in October 2026, with operation beginning in April 2028.

MEC to expand Kitakyushu plant for semiconductor package substrate chemicals

Semiconductors & electronicsFukuokaPlanned¥2B

MEC will make an additional investment in equipment at its Kitakyushu Factory, the second phase of the site's development. The expansion will address rising demand for chemicals used in semiconductor package substrates, driven in part by generative AI investment, with operations planned to start in FY2028.