Tatsuta Electric Wire to expand leak-detection system capacity at Kyoto Plant
About 11 months to scheduled completion.
Tatsuta Electric Wire will make additional capital investments at its Kyoto Plant in Fukuchiyama, Kyoto, to increase production capacity for leak-detection systems used in AI data centers and other facilities. The expansion will proceed in stages, with capacity expected to reach approximately 2.5 times the end-2026 level by September 2027, as demand for water-cooling infrastructure in AI data centers grows.
Project facts
- Listing
- 5809 Tokyo
- Facility
- Factory/Plant
- Location
- Fukuchiyama, Kyoto, Japan
- Investment
- Not disclosed
- Scale / capacity
- Approximately 2.5 times the end-2026 production capacity
- Completion
- Sep 2027
- Announced
- Oct 9, 2026
- Themes
- AI-infrastructure
Figures and schedules are as announced by the company or the public body concerned; plans can change. Amounts that were not disclosed are recorded as not disclosed, never estimated.