Chubu Electric Power to develop 1,997 kW floating solar plants in Tsu
About 16 months to scheduled completion.
Chubu Electric Power will build two floating solar power plants on agricultural irrigation ponds at two sites in Tsu, Mie Prefecture. The plants will have combined generation capacity of 1,997 kW and are scheduled to begin operations in October 2027 and February 2028.
Project facts
- Listing
- 9502 Tokyo
- Facility
- Power plant
- Sector
- Power & energy
- Location
- Tsu, Mie, Japan
- Investment
- Not disclosed
- Scale / capacity
- 1,997 kW total generation capacity; 2.442 MW total panel capacity; approximately 3.086 million kWh/year expected generation
- Completion
- Feb 2028
- Announced
- Oct 15, 2026
- Themes
- renewable-energy
Figures and schedules are as announced by the company or the public body concerned; plans can change. Amounts that were not disclosed are recorded as not disclosed, never estimated.