JScope
Factory/PlantAutomotive & transportOverseas

Toyota to build new plant building in Texas, shifting large truck production from Mexico

Toyota Motor CorporationSan Antonio, TexasPublished
Investment$3.6B
PhasePlanned
Start—
CompletionJan 2030
To completion
Today
2027202820292030

About 39 months to scheduled completion.

Toyota Motor North America announced construction of a new plant building at its Texas vehicle plant, set to begin operations in 2030. The facility will handle part of the production of the Tacoma pickup truck, currently strong in US demand, shifting output from Mexico. Total investment is $3.6 billion (approx. JPY 580 billion).

Project facts

Owner
Toyota Motor Corporation
Listing
7203 Tokyo
Facility
Factory/Plant
Sector
Automotive & transport
Location
San Antonio, Texas (overseas)
Investment
$3.6B — total
Scale / capacity
2,000 new jobs; approx. 150,000 additional annual units; 2.5 million sqft expansion, doubling plant size by 2030
Completion
Jan 2030
Announced
Jul 6, 2026
Themes
reshoring

Figures and schedules are as announced by the company or the public body concerned; plans can change. Amounts that were not disclosed are recorded as not disclosed, never estimated.

More from Toyota Motor Corporation2 projectsCompany profile →

Also in Texas2 projectsOn the map →

Latest in Automotive & transportAll Automotive & transport →

Honda and Taisei to develop wireless EV charging road infrastructure for commercial vehicles

Automotive & transportFukushimaPlanned

Honda, Taisei Corporation and Taisei Rotec have developed core technology for a dynamic wireless power transfer road system that can charge EVs while driving, including heavy commercial vehicles. The partners plan to build a test track at Taisei's T-FIELD/TAMURA facility from late 2026 and participate in a public-road demonstration on the Tateyama Expressway in Chiba from FY2027 onward.

Daiichikosho to install 50 kW EV fast chargers at about 60 Tokyo parking facilities

Automotive & transportTokyoPlanned

Daiichikosho will progressively install Terra Charge's 50 kW EV fast chargers at approximately 60 of its The Park coin-operated parking facilities in Tokyo. The installations are scheduled to be completed by the end of March 2027, adding charging infrastructure across the company's parking network.

Toyoda Gosei to build automotive interior and exterior parts plant in Maharashtra

Automotive & transportMaharashtraPlanned¥9.3B

Toyoda Gosei will establish a new factory at the Bidkin Industrial Park in Maharashtra, India, to produce bumpers, instrument panels, airbags, steering wheels and resin fuel-filler pipes. Production is scheduled to start in the first half of 2029, supporting capacity expansion by Japanese automakers including Toyota Kirloskar Motor.

Yorozu to expand production capacity at Oita Manufacturing Center

Automotive & transportOitaPlanned¥3B

Yorozu will invest approximately ¥3 billion to build a new building within its existing Oita Manufacturing Center site and install a 2,000-ton press. The expansion will increase capacity for automotive suspension and other parts, with operations planned to begin in October 2028.