ZEON to build new single-wall carbon nanotube plant at Tokuyama
About 15 months to scheduled completion.
ZEON has started construction of a new single-wall carbon nanotube (SWCNT) plant at its Tokuyama Factory in Shunan, Yamaguchi. The plant will use an advanced proprietary process based on the Super Growth method and is expected to begin full-scale operations in 2028, expanding production capacity several dozen times from the current level to meet growing lithium-ion battery demand.
Project facts
- Owner
- Zeon Corporation
- Listing
- 4205 Tokyo
- Facility
- Factory/Plant
- Sector
- Materials & chemicals
- Location
- Shunan, Yamaguchi, Japan
- Investment
- Not disclosed
- Scale / capacity
- Several dozen times current production capacity
- Construction start
- Aug 25, 2026
- Completion
- Jan 2028
- Announced
- Aug 25, 2026
- Themes
- EV-battery, AI-infrastructure, renewable-energy
Figures and schedules are as announced by the company or the public body concerned; plans can change. Amounts that were not disclosed are recorded as not disclosed, never estimated.