Factory/PlantPower & energy

Aisin and partners launch regional e-methane and CO2 recycling demonstration

Aisin CorporationNishio, AichiPublished
InvestmentNot disclosed
PhasePlanned
StartOct 2026
CompletionMar 2031
Construction
Today
20272028202920302031

Construction starts in about 1 months; completion is scheduled about 53 months from now.

Aisin, Toho Gas, Toyo Construction and Sumitomo Mitsui Banking Corporation will conduct a regional demonstration covering CO2 capture and liquefaction at industrial plants, e-methane production and supply, and CO2 fixation at a coastal landfill. The project will run from October 2026 through March 2031 and includes establishing operations to fix 1,000 tonnes of CO2 annually at the landfill.

Project facts

Owner
Aisin Corporation
Listing
7259 Tokyo
Facility
Factory/Plant
Sector
Power & energy
Location
Nishio, Aichi, Japan
Investment
Not disclosed
Scale / capacity
1,000 tonnes of CO2 fixed annually
Contractor
Toyo Construction Co., Ltd.
Equipment / vendor
IHI Plant Co., Ltd.
Construction start
Oct 2026
Completion
Mar 2031
Announced
Oct 9, 2026
Themes
renewable-energy

Figures and schedules are as announced by the company or the public body concerned; plans can change. Amounts that were not disclosed are recorded as not disclosed, never estimated.

Also in Aichi9 projects · ¥17.5B disclosedOn the map →

Latest in Power & energyAll Power & energy →

Mitsui Fudosan and TEPCO Energy Partner complete Nihonbashi 1-chome Energy Center

NewPower & energyTokyoCompleted

Mitsui Fudosan and TEPCO Energy Partner completed the Nihonbashi 1-chome Energy Center in Tokyo on September 30, 2026, and began supplying electricity and heat to the Tokyo Midtown Nihonbashi district on October 1. The facility combines cogeneration, heat-recovery chillers and thermal storage, with an AI-enabled energy management system, to improve resilience and reduce district CO2 emissions by approximately 25%.

Keiyo Gas launches 2 MW/8 MWh grid-scale battery storage facility in Isesaki

Power & energyGunmaCompleted

Keiyo Gas opened its first domestic grid-scale battery storage facility in Isesaki, Gunma, beginning full-scale operation on October 1, 2026. The 2 MW, 8 MWh high-voltage facility is operated by KG BESS LLC and was developed and constructed by Sun Village; Marubeni New Power handles market transactions as aggregator.

Chubu Electric Power starts commercial operation of Noba Solar Power Plant in Hachinohe

Power & energyAomoriCompleted

KC-22 Investment, jointly funded by Chubu Electric Power and Komata Construction, completed construction of the Noba Solar Power Plant in Hachinohe, Aomori, and began commercial operation on October 1, 2026. The plant has 1,990 kW of generating capacity and is expected to produce approximately 3.4 million kWh annually.