MonotaRO installs rooftop solar power system at Ibaraki logistics center
MonotaRO began operating a self-consumption solar power system at its Ibaraki Chuo Satellite Center in Ibaraki Prefecture, with 531.2kW capacity expected to generate about 534,000 kWh annually, covering roughly 25% of the facility's power consumption. The project supports the company's climate target of cutting CO2 emissions 50% by 2030 versus 2020 levels.
Project facts
- Owner
- MonotaRO Co., Ltd.
- Listing
- 3064 Tokyo
- Facility
- Logistics facility
- Location
- Ibaraki-machi, Ibaraki, Japan
- Investment
- Not disclosed
- Scale / capacity
- 531.2 kW solar panel capacity, approx. 534,000 kWh/year generation
- Contractor
- Looop Inc.
- Completion
- Jul 22, 2026
- Announced
- Jul 22, 2026
- Themes
- renewable-energy