J-POWER to build GPU data center in Kaminokuni, Hokkaido
About 9 months to scheduled completion.
J-POWER has decided to develop and operate its first data center, the Kaminokuni Data Center project, in Kaminokuni, Hokkaido. The facility will use GPU-equipped servers, cooling systems and 40-foot containers to sell computing capacity for generative AI development and simulations, with service launch planned for summer 2027.
Project facts
- Listing
- 9513 Tokyo
- Facility
- Data center
- Sector
- IT & telecom
- Location
- Kaminokuni, Hokkaido, Japan
- Investment
- Not disclosed
- Contractor
- Mirait One Corporation
- Equipment / vendor
- NVIDIA
- Completion
- Jul 2027
- Announced
- Aug 17, 2026
- Themes
- AI-infrastructure, renewable-energy
Figures and schedules are as announced by the company or the public body concerned; plans can change. Amounts that were not disclosed are recorded as not disclosed, never estimated.