Kawada Industries installs 519.68 kW solar PPA system at Yasui Factory
Kawada Industries introduced an on-site solar power purchase agreement system at its Yasui Factory in Nanto, Toyama, starting September 1, 2026. The system is expected to generate 526,900 kWh annually, with surplus electricity supplied to three other Kawada facilities in the Toyama area.
Project facts
- Listing
- 3443 Tokyo
- Facility
- Power plant
- Sector
- Power & energy
- Location
- Nanto, Toyama, Japan
- Investment
- Not disclosed
- Scale / capacity
- 519.68 kW panel capacity; 444.40 kW power conditioner capacity; 526,900 kWh annual expected generation
- Completion
- Sep 2026
- Announced
- Oct 1, 2026
- Themes
- renewable-energy