JScopeJapan Capex

Dynapac commissions 100 kW rooftop solar system at Toki facility

Power & EnergyGifurenewable-energy

Dynapac installed an owner-operated rooftop solar power system at Toki Dynapac in Toki, Gifu, which began operation on July 10, 2026. The 215-panel system has 100 kW output and is expected to generate approximately 100,000 kWh annually, covering about 4% of the facility's electricity demand.

Company
Dynapac Co., Ltd.
Location
Gifu, Toki
Capacity
100 kW output; approximately 100,000 kWh/year
Announced
Jul 24, 2026
Ticker
3947
Phase
completed
Completion
Jul 10, 2026
Want the full picture?See what you get

Related news

More in Power & Energy

MEL starts commercial operation of 3.4 MW Pungga small hydropower plant in North Sumatra

NewPower & EnergyNorth Sumatra, IndonesiaCompleted

PT Mulya Energi Lestari has started commercial operation of its 3.4 MW run-of-river Pungga small hydropower plant in North Sumatra, Indonesia. The facility supplies renewable electricity to Indonesia's state-owned utility PLN under a long-term power purchase agreement and is expected to reduce greenhouse-gas emissions by 8,863 tCO2 annually; EnBio Holdings participates through its jointly managed investment vehicle Alamport Renewables.

Local Energy System completes Japan's first bark-based black pellet plant in Saijo

Power & EnergyEhimeCompleted

Local Energy System, backed by Kumagai Gumi, Kiyomoto Iron Works and Shinsho Corporation, completed a black bark pellet manufacturing plant in Saijo, Ehime. The plant uses bark from sawmills to produce wood pellets and thermally processes them into black bark pellets for power-generation and industrial applications; trial operations will continue through September 2026, with commercial operations planned from October 2026.

Intellect starts construction of Togusa Solar Power Plant in Kikuyo, Kumamoto

Power & EnergyKumamotoUnder construction

Intellect is responsible for the design and construction of the Togusa Solar Power Plant in Kikuyo, Kumamoto. A safety prayer ceremony was held on July 3, 2026, marking the start of construction; the project's capacity and investment amount were not disclosed.

Arata installs 589.84 kW solar power system at Kyushu South Center

Power & EnergyKagoshimaCompleted

Arata installed a self-consumption solar power generation system under a power purchase agreement at its Kyushu South Center logistics facility in Kagoshima. The system began operating in February 2026, with planned annual generation of 603,707 kWh and surplus electricity supplied to the surrounding area as CO2-free power.